Seattle Airport Project
| Project Company | Manson Construction Company |
| Problem | This project had to pull 2,000 wood piles and drive 600 new one on a tight time schedule for a 400' addition to Terminal #5 in Seattle, Washington. The top of the piles were 50' underwater. |
| Solution | Manson & I.C.E.'s solution was to design and build a 60' long extension which bolted between the I.C.E. Model 416 vibrator and the I.C.E. Model 50 wood pile clamp. |
| What the Client Says | "From January 2nd to March 4th, with the help of the I.C.E. equipment and experience, we were able to pull 2,000 piles and drive 600 piles. It would have been impossible to do with any other equipment in that time frame." Dale Nielsen |